煤炭工程 ›› 2025, Vol. 57 ›› Issue (6): 115-125.doi: 10. 11799/ ce202506015

• 生产技术 • 上一篇    下一篇

切顶沿空留巷下采空区瓦斯抽采钻孔参数优化

张永进,年军,赵博,等   

  1. 1. 太原理工大学 安全与应急管理工程学院,山西 太原 030024

    2. 山西焦煤集团有限责任公司 博士后工作站,山西 太原 030021

  • 收稿日期:2024-06-20 修回日期:2024-08-18 出版日期:2025-06-11 发布日期:2025-07-15
  • 通讯作者: 年军 E-mail:njmkws@163.com

Optimization of borehole parameters for goaf gas extraction under roof cutting gob-side entry retaining

  • Received:2024-06-20 Revised:2024-08-18 Online:2025-06-11 Published:2025-07-15

摘要:

为确定吉宁煤矿2109工作面采空区高位钻孔的最佳布置参数,分析了切顶沿空留巷下2109 工作面完整的覆岩运动过程,研究了采空区在切顶沿空留巷Y型通风下的瓦斯分布规律,并对高位钻孔高度、间距等参数进行了优化。研究结果表明:切顶沿空留巷条件下裂隙带具有非对称性发育特征,切顶侧垮落带和裂隙带最大高度为22m和82m,未切顶侧垮落带和裂隙带最大高度为20m和86m。瓦斯在Y型通风下主要分布于采空区深部,且富集区位于未切顶侧裂隙带内,最大瓦斯浓度为42%。进一步确定了高位钻孔的最佳高度、间距分别为70m和20m,在该参数下经过160d抽采,回采工作面附近最大瓦斯浓度由1.94%降至0. 497%。根据2109工作面现场情况,设计了8个高位钻孔对采空区瓦斯进行抽采,在抽采初期,1—8号钻孔单日抽采量均呈逐渐增大的趋势,符合未抽采前瓦斯分布情况,且抽采结束后位于未切顶侧的4—8号抽采量大于位于切顶侧1—3号的抽采量,印证了切顶留巷条件下的瓦斯富集规律。

关键词:

切顶沿空留巷 , Y型通风 , 高位钻孔 , 瓦斯抽采 , 数值模拟

Abstract:

Abstract: In order to determine the optimal layout parameters of the high level borehole in the goaf of 2109 working face of Jining Coal Mine, the complete overlying rock movement process under the goaf of 2109 working face is analyzed, and the gas distribution law under the Y-type ventilation in the goaf is studied. The results show that: (1) The fracture zone has asymmetric development characteristics under the condition of goaf retaining, the maximum height of the caving zone and fracture zone on the cut side is 22 m and 82 m, and the maximum height of the caving zone and fracture zone on the uncut side is 20 m and 86 m. (2) Gas is mainly distributed in the depth of the goaf under Y-type ventilation, and the rich area is located in the fracture zone on the side of the uncut top, and the maximum gas concentration is 42%. (3) The optimum height and spacing of the upper borehole are further determined to be 70 m and 20 m, respectively. Under this parameter, the maximum gas concentration near the mining face decreases from 1.94% to 0.497% after 160 days of pumping. (4) According to the site conditions of the working face 2109, eight high level boreholes were designed to extract gas from the gob. In the early stage of extraction, the daily extraction volume of boreholes 1 to 8 showed a gradual increase, which was in line with the distribution of gas before extraction. After extraction, the extraction volume of holes 4 to 8 on the uncut top side was greater than that of holes 1 to 3 on the cut top side. The law of gas enrichment under the condition of cutting roof and retaining roadway is confirmed, which can provide reference for gas extraction in the gob under Y ventilation.